Skip to content
BIMpedia
Chapter 1 · Lesson 3 of 5Topic: The design team

What structural engineers do, and need from you

Structural engineers make the building stand up. Their model shows what can't move without calculations, and every hole, chase and heavy load is a question they have to answer.

3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Mayainformation manager
Even if you do this every day, watch for this: Holes through structure are design, not modelling. A penetration that 'looks fine' in the federated model still needs the engineer's approval and often a detail; send the list of builders' work holes as a deliverable, not as clashes to be waved through.

Structural engineers design the frame that carries the building: foundations, columns, beams, slabs and load-bearing walls. Their decisions are backed by calculations, which is why their elements are the hardest to move and the most expensive to change late.

Basics

Loads (people, furniture, plant, snow, wind) travel from slabs to beams, to columns, to foundations. Change a load, or cut a hole in a member, and the engineer may need to re-check the members below it. That's why they ask about weights, openings and positions.

What structural engineers need from you

NeedWhy
Builders' work holes (size, position, purpose) earlyEach one is checked and may need a detail or reinforcement
Plant and equipment weights and locationsLoads drive slab and beam design
Agreed grids and levelsThe frame is set out from them
Coordination on the physical modelTheir analytical model isn't for clashes
Story · The holes nobody asked about
How it goes wrong

The MEP subcontractor's coordinator resolves 120 duct-beam clashes by adding holes through the beams in the federated model and closing the issues. On site, the concrete contractor casts the beams without the openings, which were never in the structural drawings; coring them later needs the engineer's approval, a crane-hire week and two days of delay per floor.

How it goes right

The clashes are grouped into a builders' work schedule (size, position, purpose) and sent to the structural engineer as a formal request. The engineer approves 95, rejects 25 (too close to supports, so the ducts are rerouted), and issues a detail for sleeves cast in during the pour.

Mayainformation manager
Your turn. Give it about 15 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: A builders' work schedule 15 min

You have three penetrations from the latest federated model: a 300 mm duct through beam B12 at mid-span, a 150 mm pipe through a slab next to column C4, and a 600 × 400 mm duct through a core wall. List what you'd send the structural engineer for each, and which one you'd flag as most likely to be rejected.

Key takeaways

  • The structural engineer owns the frame: foundations, columns, beams, slabs, walls that carry load, and their connections.
  • Structure is the hardest thing to move late: changes need calculations, and sometimes ripple down to the foundations.
  • Openings, penetrations and heavy equipment loads must be agreed with them, with sizes and positions.
  • Their analysis model and their physical (BIM) model are different things; coordinate with the physical one.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. An MEP duct needs a 400 mm hole through a concrete beam. What's the right process?
  2. 2. Why might the structural engineer have two models?
  3. 3. A plant supplier changes a chiller to one 2 tonnes heavier. Who must be told?
0 of 3 answered