Project controls in plain words

  • Project controls compare progress against a baseline: programme (time) and budget (cost).
  • The critical path is the chain of activities that sets the finish date; delays on it delay the project.
  • Earned value compares the work planned, the work done and what it cost, to show both schedule and cost performance.
  • Model-based quantities, 4D links and progress data make controls faster and more trustworthy.

Estimating and quantity surveying

  • Estimators price designs; quantity surveyors (cost managers) manage cost through the project: cost plans, tender pricing, valuations and change.
  • They work to measurement rules (for example NRM in the UK) that may differ from how models are built.
  • Classification lets model elements map to cost items; without it, quantities can't be priced reliably.
  • Model comparison between revisions gives fast, objective change quantities.

Procurement and contracts

  • Procurement routes (traditional, design and build, management contracting, collaborative forms) decide who designs, who builds and who carries risk.
  • In design and build, design responsibility often passes from the client's designers to the contractor (novation), and so do the models.
  • Contract documents, specifications and the information protocol decide what information each party must deliver.
  • Changes cost money because contracts price a defined scope; information changes count too.