Chapter 3 recap
Money and time
The key takeaways from this chapter’s 3 lessons.
Project controls in plain words
- Project controls compare progress against a baseline: programme (time) and budget (cost).
- The critical path is the chain of activities that sets the finish date; delays on it delay the project.
- Earned value compares the work planned, the work done and what it cost, to show both schedule and cost performance.
- Model-based quantities, 4D links and progress data make controls faster and more trustworthy.
Estimating and quantity surveying
- Estimators price designs; quantity surveyors (cost managers) manage cost through the project: cost plans, tender pricing, valuations and change.
- They work to measurement rules (for example NRM in the UK) that may differ from how models are built.
- Classification lets model elements map to cost items; without it, quantities can't be priced reliably.
- Model comparison between revisions gives fast, objective change quantities.
Procurement and contracts
- Procurement routes (traditional, design and build, management contracting, collaborative forms) decide who designs, who builds and who carries risk.
- In design and build, design responsibility often passes from the client's designers to the contractor (novation), and so do the models.
- Contract documents, specifications and the information protocol decide what information each party must deliver.
- Changes cost money because contracts price a defined scope; information changes count too.