Procurement and contracts

How a project is bought (the procurement route) decides who designs what, who carries which risks, and when the contractor joins. That shapes who owns which models, when information changes hands, and what your BIM requirements can demand.

2 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Kaisite manager
Even if you do this every day, watch for this: Information requirements only bind people through their contracts. If the BIM requirements, the information protocol or the BEP aren't incorporated into each appointment and subcontract, following them is goodwill. Check the contract chain, not just the BEP.

Procurement is how the client buys the project: who it appoints, in what order, under what contracts. The route decides who designs, who builds, who carries which risks, and when information changes hands. For a coordinator, it explains why responsibilities shift halfway through a project.

Basics
RouteWho designsContractor joinsInformation impact
TraditionalClient's design team, fullyAfter designDesigners own models to tender; contractor adds its own
Design and buildClient's team starts, contractor finishes (often novated)Early or mid-designModels change owner at novation
Management contractingDesign team, packages let in stagesEarlyMany package interfaces to coordinate
Collaborative forms (alliancing, IPD)SharedFrom the startShared models and incentives

Contracts and information

  • The contract documents (drawings, specifications, information requirements) define what's being bought.
  • The information protocol brings the BIM requirements into each appointment.
  • Subcontracts must carry the same requirements down the chain.
  • Changes to information requirements after signing are changes: they can cost time and money.
Story · The models that changed hands
How it goes wrong

At novation, the architect's models move to the contractor's CDE with no agreement on what state they're in. Months later, the contractor claims the stage 4 models were incomplete; the architect says they met their old appointment. Nobody recorded what was handed over.

How it goes right

Before novation, the coordinator runs a handover review: every model and drawing, its status, a check against the stage requirements, and a list of known gaps, signed off by client, architect and contractor. The new appointment refers to it.

Kaisite manager
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Map the information handovers 10 min

A hospital is procured design and build: the client's architect and engineers reach stage 3, then are novated to the contractor, who also appoints MEP and façade subcontractors. List three points where information changes hands, and what you'd check at each.

Key takeaways

  • Procurement routes (traditional, design and build, management contracting, collaborative forms) decide who designs, who builds and who carries risk.
  • In design and build, design responsibility often passes from the client's designers to the contractor (novation), and so do the models.
  • Contract documents, specifications and the information protocol decide what information each party must deliver.
  • Changes cost money because contracts price a defined scope; information changes count too.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. In a design and build contract, what often happens to the client's design team after the contract is signed?
  2. 2. Why does the procurement route matter to the BIM coordinator?
  3. 3. A subcontractor's contract doesn't mention the information requirements. What's the risk?