FM systems and the living AIM

Will the data still be right in five years?

Handover data has to load into CAFM and CMMS systems, drive planned maintenance, and then stay current as the building changes. That's ISO 19650-3's job, and soft landings help it start well.

How it works

The process, at a glance

The asset information model in operation
AIMkept current by events
1ProjectNew or altered asset: a PIM is accepted
2MaintenanceWork orders, condition, history
3Repair or replaceAsset records updated or retired
4InspectionCompliance and condition data
5Change of useSpaces and assets re-described

Common mistakes

What goes wrong most often on real projects.

  • Assuming 'COBie compliant' means 'loads into our system'.
  • Choosing or changing the CAFM after the requirements were written.
  • An AIM that is updated by big projects but never by maintenance and minor works.
  • No aftercare: the project team leaves on completion day.

Is it in place on your project?

Tick what is done — it counts towards the checkpoint on your learning path.

0 / 4 in place