Planning, sequencing and 4D

Does the programme match the model?

Linking the programme to the model shows the sequence before it happens: logic errors, workspace conflicts, crane coverage and phasing. It only works if the model is split the way the work is.

How it works

The process, at a glance

How a programme is linked to a model
  1. 1Agree the breakdownLevels, zones, pours and work packages
  2. 2Code the programmeEach activity gets a code: L03-Z1-FRAME
  3. 3Code the modelElements carry level, zone and package properties
  4. 4Link by rulesActivity ↔ elements with matching codes
  5. 5Play and checkLogic, workspaces, logistics, every update

Common mistakes

What goes wrong most often on real projects.

  • Linking elements by hand so the 4D model breaks at the next revision.
  • A model that can't be split like the work (one slab per level when it's poured in zones).
  • Showing only permanent works and ignoring temporary works and logistics.
  • Building a 4D animation for the tender and never updating it.