From asset data to maintenance work

Every maintainable asset becomes recurring work through its maintenance regime. Getting the asset type and regime right is what turns a register into a maintenance plan.

3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Leofacilities technician
Even if you do this every day, watch for this: Criticality. Applying the maximum regime to everything makes maintenance unaffordable, so it gets cut; the critical and statutory items must be protected first.

An asset register is a list. A maintenance plan is work: thousands of tasks a year, each with a date, a skill and a cost. The link between the two is the maintenance regime each asset type follows. If the type is wrong or missing, the work is wrong or missing, every year, for the life of the building.

Regimes in practice

CategoryExampleWhy it matters
StatutoryFire alarm tests, emergency lighting tests, lift inspections, gas safetyRequired by law; missing them is a legal and safety risk
ManufacturerAHU filter changes, belt checksKeeps warranties valid
Optimal or discretionaryCondition surveys, cleaning frequenciesBalances cost and service level
Basics

Planned (preventive) maintenance is scheduled work to keep assets safe and working. Reactive maintenance fixes things after they fail. Good asset data makes the planned work accurate and the reactive work faster.

The chain from data to work

  1. The asset's type and classification in the model.
  2. A mapping from the classification to a regime (in the AIR or done by the FM provider).
  3. The asset imported to the CMMS with tag, location and product data.
  4. The regime applied; the CMMS creates work orders.
  5. History builds up against each asset.
Try it: what an asset register turns into
Planned tasks a year
1,680
Hours a year840
Full-time engineers (about 1,600 h each)0.5

Each line of asset data becomes recurring work. That's why the asset type, location and regime must be right: a missing asset is a missed inspection, and a wrong one is wasted visits for years.

Leofacilities technician
Your turn. Give it about 15 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Turn a register into work 15 min

A new office's register contains:

Asset typeCountRegime (illustration)
Fire dampers140Inspection once a year
Fan coil units420Filter change quarterly + annual service
Air-handling units6Monthly check + annual service
Emergency light fittings300Monthly function test + annual duration test
  1. How many planned tasks a year does this produce?
  2. Which tasks are statutory (in most countries) and must be protected in the plan?
  3. What happens to the plan if 30 emergency lights are missing from the register?

Key takeaways

  • A regime is a set of tasks with frequencies, skills and criticality, often from a standard library such as SFG20.
  • Each asset needs a type and classification that map to its regime.
  • Statutory tasks (fire, emergency lighting, lifts, gas) must never get lost among optional ones.
  • Asset counts multiply: small data errors become hundreds of wasted or missed visits a year.

Your notes

Related tool

Check a COBie workbook for missing sheets, blank values, duplicates and broken references.

Open COBie Checker →

Check yourself

3 questions · 2 right to complete
  1. 1. 420 fan coil units each need a quarterly filter change and an annual service. How many tasks a year?
  2. 2. Which task is statutory in most countries?
  3. 3. Fan coil units are handed over as one line, 'FCUs, various'. What's the effect?
0 of 3 answered