Designing with the model

What does a designer's model need, so everyone after them can use it?

The design model is what estimators, planners, checkers, contractors and facilities teams all build on. Model to the information they need, export IFC they can use, check your own work before it's shared, and keep the drawings in step.

How it works

The process, at a glance

A five-minute IFC check
  1. 1HeaderSchema, application, view
  2. 2Spatial structureStoreys and containment
  3. 3ClassesProxies, names, duplicates
Issuing a model: steps and gates
  1. 1
    Prepare in work in progressMandatory

    The task team finishes the model it is responsible for.

    Output: A model file named to the project convention

    Gate: Self-check done: name, coordinates, purged views and links
  2. 2
    Check the information

    Run the agreed checks: requirements (IDS), naming, clashes inside the discipline.

    Output: A short check report

    Gate: Every failure is fixed or listed as an agreed exception
  3. 3
    Share for coordinationMandatory

    Move the file to the shared area with a status code that says what it may be used for.

    Output: The model in the shared area, with a status code

    Gate: The status code matches the purpose (e.g. coordination only)
  4. 4
    Review and authorise

    The lead appointed party reviews the federated set against the plan.

    Output: Review comments, or an approval

    Gate: Approved by the person named in the BEP
  5. 5
    Publish and record

    Approved information moves to published, and the previous issue to the archive.

    Output: A published revision and an updated register

    Gate: Register and transmittal updated

A gate is the question a reviewer asks before the next step may start. If the answer is no, the model goes back one step.

Nadiaarchitect and design lead
The one I see most often on real projects: modelling detail nobody asked for, and missing the few properties everyone filters by. Tick off the checklist as you put each thing in place.

Common mistakes

What goes wrong most often on real projects.

  • Modelling detail nobody asked for, and missing the few properties everyone filters by.
  • Exporting IFC with default settings, so elements come out as proxies or without their properties.
  • Sharing a model without running the project's own checks first.
  • Moving things on drawings with 2D lines, so drawings and model disagree.