Design reviews happen on every project: the client, the fire engineer, the contractor, the operator, all looking at the design at a stage gate. In a model they can see far more than on drawings. But a review is only as good as what happens to its comments afterwards.
A stage 3 review walks through the model for two hours with eight people. Forty comments are made; the minutes list "stairs, plant access, door widths discussed". Four weeks later, three have been looked at. At stage 4 the same comments come back, more expensive.
The review has one purpose: maintenance access. The facilities manager and the mechanical engineer are invited. Each comment is saved as a BCF issue with a viewpoint, an owner and a due date. The next model is checked against the list; 37 are closed, three are carried to the next review with a reason.
A review in four steps
- Purpose: one question per review (fire, access, maintenance, cost, buildability).
- People: those who can judge it, including the operator and the contractor where they're appointed.
- Capture: each comment as an issue with a viewpoint, owner, due date and status.
- Close: check the next shared model against the list.
BCF (BIM Collaboration Format) is an open format for issues: a title, a viewpoint (camera position and the selected elements), comments and a status. Most BIM tools can read and write it, so a comment made in a viewer opens at the same spot in the designer's authoring tool.
From a review walk-through you have these notes: (a) "AHU on roof: how is it replaced?", (b) "nice entrance", (c) "check door widths on level 2 corridor", (d) "riser 3 looks tight for the ductwork". Which become issues, with what owner, and what would the viewpoint show?
Key takeaways
- Every review has a purpose (fire, access, maintenance, cost) and invites the people who can judge it.
- Comments become issues: a viewpoint in the model, an owner, a due date, a status.
- BCF carries issues between software, so comments stay attached to the place in the model.
- An issue is closed when the next model shows the fix, not when someone says it's done.