Everyone makes mistakes in a model. What matters is who finds them. When you find a missing fire rating at your desk, it takes two minutes to fix. When the fire engineer finds it during a review, it takes a meeting, a re-issue and a week. ISO 19650 puts the check before share for exactly this reason: it belongs to the team that produced the work.
The architect shares the model on Friday. On Tuesday the coordinator's IDS check fails 7 of 10 requirements. The model is rejected, the clash tests wait a week, and the structural engineer has worked against a version that's now withdrawn.
On Thursday afternoon the architect runs the project's IDS file against the export. Six walls on level 1 have no classification (a level copied from an old template) and three doors have no fire rating. Fixed in an hour. The shared model passes, with a note: "IDS 10/10, no proxies, coordinates checked."
Check against the project's own rules
- 1Prepare in work in progressMandatory
The task team finishes the model it is responsible for.
Output: A model file named to the project convention
Gate: Self-check done: name, coordinates, purged views and links - 2Check the information
Run the agreed checks: requirements (IDS), naming, clashes inside the discipline.
Output: A short check report
Gate: Every failure is fixed or listed as an agreed exception - 3Share for coordinationMandatory
Move the file to the shared area with a status code that says what it may be used for.
Output: The model in the shared area, with a status code
Gate: The status code matches the purpose (e.g. coordination only) - 4Review and authorise
The lead appointed party reviews the federated set against the plan.
Output: Review comments, or an approval
Gate: Approved by the person named in the BEP - 5Publish and record
Approved information moves to published, and the previous issue to the archive.
Output: A published revision and an updated register
Gate: Register and transmittal updated
A gate is the question a reviewer asks before the next step may start. If the answer is no, the model goes back one step.
The checklist is not yours to invent. Use:
- the IDS file or LOIN the client issued,
- the naming rules from the information standard,
- the agreed coordinates (one or two control points),
- a quick look at classes and storeys after export.
IDS (Information Delivery Specification) is a buildingSMART format for requirements: "every door must have Pset_DoorCommon.FireRating", "every space must have a name". A checker reads the IDS and the IFC and reports which elements pass or fail each requirement.
Read the result by cause
A long list of failures looks frightening. Sort it by level, type and requirement and it usually collapses into a few causes:
| Pattern | Likely cause |
|---|---|
| All failures on one level | A copied level or an old template |
| All failures on one type | The type is missing the property |
| Every element fails one requirement | An export setting or a misspelt property name |
| A few scattered elements | Genuine gaps: fix them one by one |
Open the IDS Checker on the sample. The BIMpedia Clinic is checked against its ten requirements.
- How many requirements fail?
- Group the failures by cause: which are probably one cause each, and which are scattered gaps?
- What would you write in the note when sharing, if you fixed everything but the manufacturer?
Key takeaways
- Self-checking is the 'check' in ISO 19650's WIP to shared step: it belongs to the team that produced the work.
- Use the project's own requirements (an IDS file or the LOIN) as the checklist, not your own guess.
- Look at failures by cause, not one by one: one wrong export setting can fail a thousand elements.
- Record what you checked with each issue, so the reviewer can trust it.