The superintendent (site manager in the UK and elsewhere) is the person who runs the site every day. They're responsible for safety, the sequence of work, the trades on site, deliveries and the quality of what's built. Their day is long and full of decisions; they need information that answers questions quickly and reliably.
| Time | What happens | Information needed |
|---|---|---|
| Morning | Safety and task briefing | Today's areas, hazards, sequence |
| Day | Trades build; questions come up | What goes here, at what level, approved? |
| Inspections | Work checked before covering up | Requirements, approved details |
| Weekly | Look-ahead planning | Next weeks' areas, deliveries, constraints |
What the site team needs from you
- Approved views by area: what's built where, on a tablet, offline if needed.
- Fast answers to site questions, often directly from the model.
- Clear change notices: what changed in their area since the last issue.
- Simple ways to report back: issues and progress tied to elements.
At 7 am the foreman can't find whether a drainage sleeve goes in today's pour; the drawing in the cabin is two revisions old. The pour goes ahead. A week later the sleeve has to be cored through post-tensioned slab, with an engineer's approval and a three-day stop.
The site team has a tablet view of each pour area with the approved sleeves highlighted and the latest revision status. The foreman checks the area before the pour, sees the sleeve, and sets it.
Next Tuesday, slab pour 3 on level 2 (zone B). List what you'd prepare for the superintendent and foreman.
Key takeaways
- The superintendent is responsible for the daily running of the site: safety, sequence, trades, logistics, quality.
- Their day runs on look-ahead programmes, daily briefings and inspections.
- They need simple, approved information by area: what goes here, at what level, built by whom, and what's changed.
- Site questions (RFIs) need fast answers; the model can often answer them in minutes.