Chapter 6 · Lesson 1 of 2Topic: Handover

Commissioning

Commissioning proves that the building's systems work as designed: each one is set up, tested, adjusted and demonstrated before handover. Its results are information the operator needs on day one, and they're best tied to the assets in the model.

2 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Leofacilities technician
Even if you do this every day, watch for this: Commissioning results are asset data. Test sheets in a folder of PDFs are hard to use; results linked to the asset tags (design flow, measured flow, date, who) become the operator's baseline for every future fault-finding.

Commissioning proves that the building works. Every system (ventilation, heating and cooling, water, power, lighting, controls, fire alarm and suppression, lifts, security) is checked, set up, tested, adjusted and demonstrated against the design before the building is handed over. In many projects a commissioning manager or commissioning authority leads it.

Basics
StepWhat happens
Pre-commissioningInstallation checks: complete, clean, safe to start
Testing and balancingEach system run, measured, adjusted to design values
ControlsSequences and set points tested
Integrated systems testsSystems tested together (fire mode, power failure)
WitnessingThe client, designer or authority watches key tests
HandoverResults, certificates and settings handed to the operator

Where information comes in

  • The commissioning plan lists systems, tests and responsibilities: build it from the asset list in the model.
  • Test results (design value, measured value, settings, date, who) belong with the assets.
  • Certificates (electrical, fire, lifts) are handover documents linked to the systems they cover.
  • Defects found during commissioning are issues: track them to closure.
Story · The folder of test sheets
How it goes wrong

Commissioning results arrive as 2,000 scanned test sheets in a folder. A year later, a room is too hot; the FM team can't find what the air flow was set to, and re-balances the system by trial and error.

How it goes right

Each test result is recorded against the asset tag in the asset register: design and measured flows, damper settings, date and engineer. The FM team pulls up the terminal unit, sees it was set to 180 l/s, finds it now at 110 l/s, and fixes a stuck damper in an hour.

Leofacilities technician
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Design a results record 10 min

Design the fields you'd record for each air terminal (diffuser) during commissioning, so the operator can use them later.

Key takeaways

  • Commissioning checks, tests, adjusts and demonstrates each system (ventilation, heating, power, controls, fire, lifts) against the design.
  • It follows a plan: pre-commissioning checks, testing and balancing, integrated systems tests, witnessing and handover.
  • Results (measured values, settings, certificates) are part of the handover information.
  • Linking results to asset tags turns them into the operator's baseline.

Your notes

Related tool

Build an asset register from an IFC and check it on the model: data quality in colour, a data sheet per asset, rooms and systems, a first maintenance plan and tag labels.

Open Asset Register Builder →

Check yourself

3 questions · 2 right to complete
  1. 1. What is the purpose of commissioning?
  2. 2. Why are commissioning results valuable after handover?
  3. 3. What is an integrated systems test?
0 of 3 answered