Chapter 5 recap
On site
The key takeaways from this chapter’s 4 lessons.
The general contractor
- The main contractor plans, procures, builds and coordinates the works, through a team of project managers, planners, QSs, engineers and site managers.
- Work is bought in packages (groundworks, frame, envelope, MEP, fit-out), each with its own subcontractor.
- Contractors use models for planning, logistics, quantities, package scopes, coordination of trades and site queries.
- They need information split by package, zone and level, with clear status: what's approved to build.
The superintendent and the site team
- The superintendent is responsible for the daily running of the site: safety, sequence, trades, logistics, quality.
- Their day runs on look-ahead programmes, daily briefings and inspections.
- They need simple, approved information by area: what goes here, at what level, built by whom, and what's changed.
- Site questions (RFIs) need fast answers; the model can often answer them in minutes.
Trades and subcontractors
- Specialist subcontractors (trades) design in detail, fabricate and install their packages.
- Many produce fabrication models (steel connections, MEP spools, façade panels) from the design models.
- Their models must come back into the federation for coordination before fabrication.
- Their product data is the most important source of handover information.
RFIs, submittals and inspections
- An RFI (request for information) is a formal question from site or a trade to the design team.
- A submittal is a proposal (shop drawing, product data, sample) sent for the designer's review before it's built or bought.
- Inspections check work before it's covered up or handed over; results are records.
- Linking all three to model elements makes them faster to answer, easier to find, and useful as as-built and handover data.