Trades and subcontractors

Most of the building is designed in detail, fabricated and installed by specialist subcontractors: steel, façade, MEP, lifts, joinery. They often take over models for fabrication, and their information is what the building is actually made from.

With Kai, site manager2 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Kaisite manager
Even if you do this every day, watch for this: When a trade takes design to fabrication, model ownership moves, and so does responsibility for coordination. Agree the moment it happens, what model they start from, and how their fabrication model comes back for coordination: otherwise the coordinated design model and what's built drift apart.

Most of what's built is designed in detail, made and installed by specialist subcontractors: the trades. Steel fabricators, façade specialists, MEP contractors, lift companies, joiners. On many projects they take the design models and develop them into fabrication models, and their information is what the building is actually made from.

Basics
TradeWhat they modelWhat it's used for
Steel fabricatorConnections, plates, boltsShop drawings, CNC fabrication
MEP contractorSpools, supports, fittingsPrefabrication, installation
Façade specialistPanels, brackets, jointsPanel fabrication, installation sequence
Lift companyShafts, machinery, loadsBuilders' work, coordination

Working with trades

  • Agree the handover point: which design model the trade starts from and when ownership passes.
  • Bring their models back into the federation: fabrication detail can clash with other trades.
  • Approve before fabrication: once parts are made, changes are expensive.
  • Collect product data as they go: manufacturer, model, serial, warranty, maintenance.
Story · The spools that didn't fit
How it goes wrong

The MEP contractor prefabricates pipework spools from its own fabrication model, which is never federated. On site, a third of the spools clash with the sprinkler contractor's mains, modelled separately. The spools are cut and re-welded on site, and the benefit of prefabrication is lost.

How it goes right

Every trade's fabrication model joins the weekly federation for the area being fabricated. MEP and sprinkler clashes are resolved in the models; the spools are approved, fabricated and installed without rework.

Kaisite manager
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Plan a trade handover 10 min

The façade specialist is appointed at stage 4. Write four things to agree with them about information.

Key takeaways

  • Specialist subcontractors (trades) design in detail, fabricate and install their packages.
  • Many produce fabrication models (steel connections, MEP spools, façade panels) from the design models.
  • Their models must come back into the federation for coordination before fabrication.
  • Their product data is the most important source of handover information.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. When the MEP subcontractor produces fabrication models, what should happen before fabrication?
  2. 2. Where does most product-specific handover data come from?
  3. 3. Why agree the moment model ownership passes to a trade?