Project controls answer two questions every week: are we on time, and are we on budget? They compare what was planned (the baseline) with what is happening (progress), and explain the difference. A BIM coordinator meets them through 4D, quantities, progress tracking and reporting.
| Term | In plain words |
|---|---|
| Programme (schedule) | Activities, durations and links, in order |
| Baseline | The agreed plan, kept fixed for comparison |
| Critical path | The chain that sets the finish date |
| Float | How far an activity can slip without moving the finish |
| Progress update | What's done, at a data date |
| Earned value | Planned work vs work done vs cost of the work done |
Where BIM helps controls
- Quantities from the model for budgets and progress measurement.
- 4D: the programme linked to elements, to check logic and show progress.
- Progress data from site (inspections, as-built checks) linked to elements.
- Change: model comparison shows what changed between revisions, for cost and time impact.
Progress is reported as "percent complete" estimated by each supervisor. The report says 62%; the client's advisor walks the site and thinks 50%. Arguments follow every month.
Progress is measured against model elements: slabs poured, walls built, systems installed, recorded on tablets during inspections. The report shows 54% by earned quantity, with the elements behind it; both sides agree in ten minutes.
Using the network in the exercise below (A 5 → B 8 → D 10 → G 6, with C 15 in parallel before D), on which day does the project finish?
Activities: A Excavate (5 days) → B Footings (8) → D Erect steel (10) → G Roof (6). In parallel: C Steel fabrication (15) starts day 0 and must finish before D. What's the critical path and the finish day? How much float does A have?
Key takeaways
- Project controls compare progress against a baseline: programme (time) and budget (cost).
- The critical path is the chain of activities that sets the finish date; delays on it delay the project.
- Earned value compares the work planned, the work done and what it cost, to show both schedule and cost performance.
- Model-based quantities, 4D links and progress data make controls faster and more trustworthy.