Plans, sections and details

A structure is described by views that each show part of the truth: plans from above, elevations from the side, sections cut through it, and details at larger scale. Reading a set means moving between them and checking that they agree.

With Omar, BIM coordinator3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
OmarBIM coordinator
Even if you do this every day, watch for this: Cross-check views against each other. A dimension that appears on the plan, the section and the framing plan must agree in all three; when it doesn't, you have found a coordination issue before anyone built it.

No single view shows a structure completely. A plan hides heights; an elevation hides depth; a section shows only where it is cut. A drawing set is a set of views that, together, describe one thing, and reading it means moving between them.

Basics
ViewYou are lookingShows best
PlanDown from aboveLayout, lengths, positions
ElevationFrom the sideHeights, levels, profiles
SectionAt a cut through itThicknesses, layers, how parts fit
DetailAt a small part, enlargedConnections, reinforcement, fixings

Moving between views

Sheet 4: Cross section and floor details Open full size
Sheet 4: Cross section and floor details, Benton Street Bridge drawing set

Sheet 4, cross section and floor details: a typical cross section at the floorbeams, details of girders and stringers, the exceptions at piers 2 and 3, and the framing plan along the bottom.

Benton Street Bridge, Iowa City (Ned L. Ashton, consulting engineer, 1947–48). Historic American Engineering Record, HAER IOWA,52-IOWCI,4-. Library of Congress, Prints and Photographs Division. Public domain. Source

On sheet 4 you can follow how the views relate:

  • The typical cross section gives the deck: 26'-0" clear between the upper curbs, a 24'-0" concrete roadway with a 1½" crown, a 5'-0" sidewalk, and main girders 20'-3" centre to centre.
  • The framing plan along the bottom shows the same girders from above, with 22 panels of 20'-0" between end panels of 18'.
  • Details at piers 2 and 3 show where the typical arrangement doesn't apply.
  • A callout sends you to sheet 10 for the lamp post brackets.

Check the views against each other

The fastest check of any set is arithmetic. Add up a chain of dimensions and compare it with the overall figure; find the same dimension on two sheets and compare them. On this set, sheet 4's framing plan (18' + 22 × 20' + 18' = 476') agrees with sheet 1 (476' between end bearings). When a check like this fails, one of the sheets has been edited, or is from another revision.

Sheet 3: Main piers Open full size
Sheet 3: Main piers, Benton Street Bridge drawing set

Sheet 3, the main piers. Open it full size and find the levels that tie each pier back to the general elevation on sheet 1.

Benton Street Bridge, Iowa City (Ned L. Ashton, consulting engineer, 1947–48). Historic American Engineering Record, HAER IOWA,52-IOWCI,4-. Library of Congress, Prints and Photographs Division. Public domain. Source

Story · The section nobody cross-checked
How it goes wrong

The architectural section shows a 3.0 m floor-to-ceiling height in the corridor. The services drawings, drawn from an earlier plan, assume a 600 mm ceiling void. Nobody compares the two, and on site the ducts don't fit above the corridor ceiling.

How it goes right

The coordinator cuts the same section through the federated model, lays it next to the architectural section and the services drawing, and checks three numbers: slab level, ceiling level and duct depth. The 150 mm shortfall is found in a meeting, not on site.

OmarBIM coordinator
Your turn. Give it about 15 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Read the deck section 15 min

Open sheet 4 of the Benton Street Bridge above, full size.

  1. What is the clear width between the upper curbs, and the width of the concrete roadway?
  2. The slab is noted as "7½" gross slab (½" for wear)". What thickness carries the load, in inches and in millimetres?
  3. How far apart are the main girders, centre to centre, in metres?

Key takeaways

  • Plan, elevation and section are three directions of looking at the same thing; details are close-ups at a larger scale.
  • Section marks and detail callouts tell you where a view is cut and which sheet it is drawn on.
  • 'Typical' views apply wherever nothing else is shown; exceptions are drawn separately.
  • Add up chains of dimensions and compare views: it is the fastest drawing check there is.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. A note on sheet 4 says 'Lamp post: for details see sheet #10'. What is that?
  2. 2. Sheet 4's framing plan shows '22 panels @ 20'-0" = 440'-0"' between two 18' end panels. Sheet 1 gives 476' between end bearings. What do you conclude?
  3. 3. A section is marked 'Typical cross section at floorbeams'. Where does it apply?