Chapter 3 · Lesson 4 of 5Topic: Planning and 4D

Lean planning and the Last Planner

The people who do the work plan it together, week by week, and commit only to tasks that are ready. The model's job is to show what is ready and what is still blocking.

With Kai, site manager3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Kaisite manager
Even if you do this every day, watch for this: A constraint is often information, not material. The model is where you find the missing dimension, the open clash or the unapproved shop drawing before the crew finds it on the day.

A programme says what should happen. On a busy site, what actually happens depends on whether each crew can start: are the drawings approved, is the material here, is the work before theirs finished? The Last Planner System is a lean planning method built on that question. The people who direct the work, the "last planners", plan it together and commit only to tasks that are ready.

Story · The ceiling that wasn't ready
How it goes wrong

The programme shows ceilings in level 2 zone A next week, so the site manager puts it in the weekly plan. On Monday the drylining crew arrives to find two ducts still clashing with the grid, and a sprinkler drop waiting for an approved drawing. The crew stands around for half a day, then moves to work that wasn't planned. The ductwork team, which didn't know the ceiling was coming, carries on elsewhere.

How it goes right

In the look-ahead meeting two weeks earlier, the BIM coordinator opens zone A in the model with the foremen. The two open clashes and the missing sprinkler drawing are logged as constraints, each with an owner and a date. One clash is fixed that week; the other isn't, so the foreman commits only to the part of the zone that is clear. The promise is kept.

The four levels of planning

Basics

Lean construction applies ideas from lean manufacturing to building: make work flow, remove waste (waiting, rework, moving material twice) and make handoffs between crews reliable. The Last Planner System, developed by Glenn Ballard and Greg Howell, is its best-known planning method.

LevelHorizonWhoWhat comes out
Master scheduleWhole projectPlanner, project leadersMilestones
Phase (pull) planOne phase, to a milestoneAll trades in the phaseAgreed handoffs, worked back from the milestone
Look-aheadAbout six weeksForemen, coordinatorTasks screened for constraints, constraints removed
Weekly work planNext weekForemenCommitments to ready tasks only

Each week, the team checks which commitments were kept. PPC (percent plan complete) is commitments kept divided by commitments made. A missed commitment gets a reason (drawing late, material not delivered, previous work not finished), and the reasons are tracked to fix the causes.

Building a pull plan

Pull planning starts at the milestone and works backwards. Each trade puts its tasks on the board, saying what it needs from the trade before it to start. The handoffs are agreed between the people who will make them.

Kaisite manager
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Pull-plan the clinic roof 10 min

The milestone is "roof watertight, zone B". Put the tasks in the order the trades would agree them.

Check yourself

Pull-plan the roof

Milestone: roof watertight, zone B. Put the tasks in the order the trades would agree them.

  1. 1Roof slab poured
  2. 2Level 2 frame complete
  3. 3Roof watertight
  4. 4Membrane laid
  5. 5Upstands and outlets formed
  6. 6Slab cured and handed over

Then decide which of these is a constraint for the roofing crew: "Roof slab in zone B not yet poured", "Membrane delivered to site", "Crane booked for the day".

Key takeaways

  • Pull planning works back from a milestone; each trade says what it needs from the one before.
  • A task is ready only when its constraints are gone: information, materials, access, the work before it.
  • PPC (percent plan complete) measures kept promises, not progress against the programme.
  • Use the model to show a zone's sequence in pull planning and to find missing information in the look-ahead.

Your notes

Related tool

Play your programme (P6 or MS Project) on the IFC model: see it built day by day, find late work and sequence errors.

Open 4D Simulator →

Check yourself

3 questions · 2 right to complete
  1. 1. In the weekly meeting, the drylining foreman wants to commit to boarding level 2 zone A next week. The services above the ceiling there still have two open clashes. What should happen?
  2. 2. Last week the trades made 40 commitments and kept 30. The project is two weeks ahead of the master programme. What is the PPC?
  3. 3. During pull planning for the roof milestone, how does the model help most?
0 of 3 answered