Chapter 1 · Lesson 3 of 3Topic: Constructability

IPD and the big room

When the owner, designers and builders share one agreement and one room, the model stops being handed over and starts being worked on together. Here is what changes for the BIM person.

With Kai, site manager3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Kaisite manager
Even if you do this every day, watch for this: The big room fails quietly when the model on the wall is a week old. The coordinator's job is to make sure the model people decide on is the current one.

Most projects pass the model from one party to the next: the designers model, the contractor checks, the trades remodel for fabrication. Integrated project delivery (IPD) works differently. The owner, the lead designers and the builder, often with key trades, sign one agreement, and their profit depends on how the whole project turns out. They work together from early design, usually in a shared office called the big room.

Basics

Under IPD, costs are reimbursed and profit goes into a shared pool, paid against targets for cost and quality. Liability between the parties is often limited. Decisions are taken by a joint team with members from each party. See the IPD entry for the details.

Story · The riser on the wall
How it goes wrong

On a design-bid-build hospital, the architect issues the riser layout. Eight months later, the mechanical subcontractor models its ductwork and finds the riser 300 mm too narrow. An RFI goes back to the design team, a variation follows, and the argument over who pays takes longer than the redesign.

How it goes right

On an IPD hospital, the mechanical trade models the main ducts during design development. In the big room, the coordinator puts the federated model on the screen; the riser is visibly too tight. The architect, the structural engineer and the mechanical foreman agree a wider riser in twenty minutes, and the decision is logged with its effect on the cost target.

What changes for the BIM person

In a traditional projectIn IPD and the big room
Designers model, then hand overDesigners and trades model the same zones at the same time
Clash reports go out by emailClashes are resolved on screen with the people who can decide
Trades remodel for fabricationTrade models are the design models, developed to fabrication
Decisions in RFIs and minutesDecisions logged in the room, against the model and the target

Borrowing the habits

Few projects use full IPD. Many borrow its habits under ordinary contracts: early contractor and trade involvement, a weekly coordination session on the shared model, decisions logged with the model view that prompted them.

Kaisite manager
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Plan a big-room week 10 min

You coordinate a clinic project under ordinary contracts, but the client wants "big-room working". Sketch the week: which sessions, who attends, and what the model must show at each.

Check yourself

A big-room week

Put the week’s sessions in a sensible order.

  1. 1Coordination session: open issues decided on screen
  2. 2Model refresh: every team uploads, the coordinator federates
  3. 3Cost and programme check against the week’s decisions
  4. 4Look-ahead with the foremen: what is missing for the next weeks

Key takeaways

  • Under IPD, the owner, designers and builders share one agreement, and their profit depends on the whole project.
  • The big room is where decisions happen: the federated model is on the wall, and the people who can decide are in the room.
  • Trades model early, so coordination moves from 'design, then check' to 'design together'.
  • Even without IPD, borrow the habits: early trade input, a shared model, decisions logged in the room.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. On an IPD hospital, the mechanical trade finds that a riser is too small. In a traditional contract it would be a variation. What usually happens in the big room?
  2. 2. What is the BIM coordinator's most useful job in the big room?
  3. 3. Your project has ordinary two-party contracts. Which IPD habit can you still borrow?
0 of 3 answered
Next lessonChapter 1 recap