Reporting the cost of change

Design changes cost money, and the model knows exactly which elements changed. Compare each revision with a baseline, price the difference, and check what the quantities can't see.

3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Priyaestimator
Even if you do this every day, watch for this: Measurement blind spots. Before trusting a change total, ask what each quantity counts; counts and lengths hide size changes.

Design changes are normal; surprises about their cost aren't. Because the model knows which elements changed between revisions, the cost of a change can be worked out the day the revision arrives, not weeks later. But only if the comparison is set up properly, and someone checks what the numbers can't see.

Story · The saving that wasn't
How it goes wrong

Revision B arrives with larger south windows. The take-off reports 40.5 m² less external wall: a saving of about 11,500. The change is approved as cost-neutral. At final account, the glazing subcontractor's bill for the larger windows is about 38,000 more.

How it goes right

The cost manager compares revision B with the priced baseline in the model. The walls show the saving; the windows show "unchanged" because they're counted by number. Looking at the elements in 3D, the windows are visibly bigger. The report prices the extra glazing area separately and the change is approved at a net cost of about 27,000.

The change report, step by step

From model to estimate
  1. 1
    Classify

    Every measured element carries a classification code

    Output: Classified model

    Gate: No unclassified elements in measured categories
  2. 2
    Extract

    Quantities per type: count, length, area, volume

    Output: Quantity table

    Gate: Duplicates between models removed
  3. 3
    Map

    Types to cost items by classification

    Output: Measured items

    Gate: Every type mapped, net and gross stated
  4. 4
    Price

    Rates per cost item

    Output: Priced items

    Gate: Rates current, source stated
  5. 5
    CompleteMandatory

    Add what the model can’t give: preliminaries, risk, unmodelled items

    Output: Estimate

    Gate: Report says what came from the model and what didn’t

Each step has an output and a check. The estimate is only as good as the weakest gate.

  1. Save the baseline when a revision is priced and agreed.
  2. Open the new revision: every item shows its change against the baseline.
  3. Look in 3D at the changed elements, and at the ones you'd expect to change.
  4. Price the difference with the estimate's rates.
  5. Write the report: what changed, why, its cost, and what isn't included.
Basics

Every IFC element has a GlobalId that should stay the same across revisions. Tools compare revisions by matching these IDs: added, removed and changed elements. If an authoring tool regenerates IDs on export, every element looks new; check that first.

Priyaestimator
Your turn. Give it about 15 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Price revision B of the clinic 15 min

Open Quantity Take-off and 5D on the sample (sample rates are filled in). Save it as a baseline, then load Sample: revision B and choose Change since baseline.

  1. What does the take-off say the change costs?
  2. Which elements change colour in 3D, and which change can you see that the colours miss?
  3. What's a fair cost for the change, and how would you report it?

Key takeaways

  • Every change report compares two revisions element by element, against a saved baseline.
  • Price the change from the same rates as the estimate, so the numbers reconcile.
  • Some changes don't show in quantities (a bigger window counted as one window); check what each quantity measures.
  • Report the change with its cause, its cost and what's not included, before it's approved.

Your notes

Related tool

Quantities and costs on the 3D model: colour by cost, find what can't be measured, see each revision's change and when the money is spent.

Open Quantity Take-off and 5D →

Check yourself

3 questions · 2 right to complete
  1. 1. Revision B enlarges the south windows. The take-off shows less external wall and the same number of windows. What's the risk?
  2. 2. Why compare revisions against a saved baseline?
  3. 3. What should a change report always include?