Chapter 5 recap

Safety and project controls

The key takeaways from this chapter’s 4 lessons.

Safe sequencing with 4D

  • Look at each week of the 4D model for people, not just elements: who works where, and what is above them.
  • Stacked trades, lifts over occupied areas and open edges show up clearly when you play the programme.
  • Each problem found becomes a change to the sequence, a temporary work, or an exclusion zone in the logistics model.
  • Review the 4D model with the site manager and the safety advisor before each look-ahead.

Health and safety information at handover

  • The health and safety file holds what future workers need to know: residual risks, hazardous materials, how to access and remove things safely.
  • Information linked to elements and assets is found when someone works on them; a separate PDF usually isn't.
  • Keep it short and specific: the risk, where it is, and what to do.
  • Agree early who provides each part and check it at every milestone, like any other asset information.

Progress against the plan

  • Progress measured on elements (built or not, by zone) is more objective than a percentage someone estimates.
  • Planned value, earned value and actual cost compare what should be done, what is done, and what it cost.
  • The 4D model shows the planned state on any date; actual dates show where the job really is.
  • Report by zone and package, with the two or three numbers that lead to decisions.

Reporting the cost of change

  • Every change report compares two revisions element by element, against a saved baseline.
  • Price the change from the same rates as the estimate, so the numbers reconcile.
  • Some changes don't show in quantities (a bigger window counted as one window); check what each quantity measures.
  • Report the change with its cause, its cost and what's not included, before it's approved.