Coordinates over long corridors

A map grid is a flat picture of a curved Earth, so distances on the grid differ slightly from distances on the ground. Over a building nobody notices; over a 20 km railway it adds up to decimetres or metres. The scale factor turns one into the other.

With Maya, information manager3 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Mayainformation manager
Even if you do this every day, watch for this: Agree with the surveyor, in writing, whether design coordinates are grid or ground, and which combined scale factor applies where. Most corridor errors come from one team working in grid and another in ground without knowing it.

A building is small enough that the Earth is flat for its purposes. A railway or a pipeline isn't. Map grids flatten the curved Earth onto a plane, and that flattening stretches distances slightly in some places and shrinks them in others. On a long corridor, the difference between a distance on the grid and the same distance on the ground becomes a design problem.

Basics
TermMeaning
Grid distanceDistance computed from map grid coordinates
Ground distanceDistance actually measured on site, at the site's height
Grid scale factorGrid ÷ ellipsoid distance at a place on the projection
Elevation factorCorrects for height above the ellipsoid
Combined scale factorGrid scale factor × elevation factor

How big is the difference?

National grids are designed to keep the scale factor close to 1: typically within a few hundred parts per million (ppm) across the country. A factor of 0.99985 is −150 ppm: every kilometre on the grid is 1,000.150 m on the ground. Over a 300 m building that's 45 mm, often ignored. Over a 20 km route it's 3 m.

Route lengthError at 150 ppm
300 m45 mm
1 km150 mm
10 km1.5 m
20 km3.0 m

Three ways projects handle it

  1. Work in grid, convert for set-out. Models in the national grid; the surveyor applies the combined factor when setting out. Simple, but every team must know.
  2. Work in ground, tie to grid. Models at true size; a documented transformation (with scale) maps them to the grid. Common for buildings and short structures.
  3. A low-distortion project grid. A projection designed around the route so the factor stays within a few ppm everywhere. Used on many long rail and road schemes.

Whichever you choose, write it on the georeferencing sheet: the CRS (EPSG code), whether model units are grid or ground, the combined factor by zone, and who maintains them.

Story · Three metres at the far end
How it goes wrong

The viaduct designers model at true ground size from a local origin at the south end. The track designers work in national grid. Nobody records a scale factor. At the north end, 20 km away, the viaduct's last pier and the track alignment disagree by 3 m.

How it goes right

At mobilisation the surveyor issues a project grid with a stated factor of 1.000002 along the whole route, and every model is built in it. The viaduct and the track agree to millimetres at both ends.

Mayainformation manager
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Grid or ground? 10 min

A pipeline runs 8.4 km. The surveyor gives a combined scale factor of 0.99978 for the route.

  1. The design gives a grid distance of 8,400.000 m. What is the ground distance?
  2. How many metres of pipe would be short if it were ordered from the grid length?
  3. What would you write on the georeferencing sheet so no team repeats the mistake?

Key takeaways

  • Projected grids distort distances slightly; the grid scale factor says by how much at each place.
  • Height above the datum adds an elevation factor; together they make the combined scale factor.
  • Ground distance = grid distance ÷ combined scale factor (for factors close to 1).
  • Long projects often use a low-distortion project grid so that grid and ground almost match.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. A grid distance of 1,000.000 m is measured where the combined scale factor is 0.99985. What is the distance on the ground?
  2. 2. The structures team sets out from model dimensions (ground); the track team works in grid coordinates. On a 15 km route, what will happen?
  3. 3. Why do some long rail projects define their own project grid?