Alignments and chainage

On a linear project, everything is located by its distance along the alignment and its offset from it. That distance is called chainage (or stationing in the US, mileage on older railways). Learn to read it, and to check a vertical curve from a real drawing.

With Maya, information manager4 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Mayainformation manager
Even if you do this every day, watch for this: Chainage belongs to one named alignment. When the alignment is redesigned, chainages move; a structure located only by chainage can end up in the wrong place. Record which alignment and which revision every chainage refers to.

On a building you locate things by grids and levels. On a road, a railway or a pipeline you locate them by how far along the line they are, and how far to the side. That line is the alignment, and the distance along it is the chainage.

Basics
TermMeaning
Horizontal alignmentThe line in plan: straights, circular curves, transition curves
Vertical alignment (profile)Levels along the line: grades and vertical curves
Chainage / stationingDistance along the alignment from its start
OffsetDistance left or right of the alignment, at right angles
PIPoint of intersection, where two straights or two grades meet

How chainage is written

WhereWrittenMeans
US (feet)Sta. 5+10510 ft
MetricCh 1+250 or 1+250.0001 km and 250 m = 1,250 m
UK railways (traditional)12 m 40 ch12 miles 40 chains (1 chain = 22 yards ≈ 20.12 m)

A structure on the line is located as "chainage, offset": for example Ch 2+340, 4.5 m left.

A real profile

Sheet 1: General plan and elevation Open full size
Sheet 1: General plan and elevation, Benton Street Bridge drawing set

Sheet 1 of the Benton Street Bridge. The elevation is a profile along the road: stations from Sta. 0+00, a 2.5% grade up, a 320 ft vertical curve with its PI at Sta. 5+10, El. 70.10, and a 2.5% grade down.

Benton Street Bridge, Iowa City (Ned L. Ashton, consulting engineer, 1947–48). Historic American Engineering Record, HAER IOWA,52-IOWCI,4-. Library of Congress, Prints and Photographs Division. Public domain. Source

The elevation on sheet 1 is a profile along Benton Street. It gives stations (the east backwall face at Sta. 2+70, the west one at Sta. 7+50), the grades (+2.5% up and −2.5% down) and a 320 ft vertical curve with its PI at Sta. 5+10, El. 70.10. The crown of the road at midspan is written as El. 68.1. In the exercise you'll check that number yourself.

Alignments in open BIM

IFC 4.3 adds IfcAlignment, with its horizontal, vertical and cant (for rail) parts, so a bridge or a station can be placed by its position along the alignment and exchanged with that reference intact. Before IFC 4.3, alignments travelled mostly in LandXML or in each vendor's own format.

Story · The culvert that moved
How it goes wrong

Culverts are located in the drainage schedule only by chainage. The road alignment is redesigned around a new junction and becomes 40 m longer before the river. The schedule isn't updated; the culverts are set out at their old chainages, 40 m short of the watercourses they were meant to carry.

How it goes right

The drainage schedule records each culvert's chainage with the alignment name and revision, and its coordinates. When the alignment changes, a check flags every item referenced to the old revision, and the culverts are re-chained before anything is set out.

Mayainformation manager
Your turn. Give it about 15 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Check the bridge's vertical curve 15 min

From sheet 1 of the Benton Street Bridge: grades of +2.5% and −2.5% meet at a PI at Sta. 5+10, El. 70.10, with a 320 ft symmetrical vertical curve.

  1. At which stations does the vertical curve start and end?
  2. What is the level of the road at the middle of the curve? Compare with the drawing.
  3. How far from the PI is the high point?

Key takeaways

  • An alignment is a horizontal line (straights, curves, transitions) plus a vertical profile (grades and vertical curves).
  • Chainage or stationing is the distance along it; offsets are left or right of it.
  • US stations are written in hundreds of feet (Sta. 5+10 = 510 ft); metric chainage in kilometres and metres (Ch 1+250).
  • A chainage only means something with its alignment name and revision; IFC 4.3 carries alignments as IfcAlignment.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. A drawing gives 'Sta. 7+50'. How far along the alignment is that?
  2. 2. The road alignment is redesigned and lengthened by 40 m before a culvert. The culvert was located only by its chainage. What happens?
  3. 3. On a symmetrical crest vertical curve, grades of +2.5% and −2.5% meet at a PI at El. 70.10 over a 320 ft curve. What is the level at the middle of the curve?
0 of 3 answered