Chapter 5 · Lesson 3 of 4Topic: Health and safety

Health and safety information through the project

Safety information is information like any other: required, planned, produced, checked and handed over. When the information manager treats it that way, the health and safety file builds itself; when nobody does, it's compiled in a panic at the end.

4 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Tomhealth and safety advisor
Even if you do this every day, watch for this: Give safety information a home on day one. Decide in the EIR where design risks, residual risks and hazardous materials live (which containers, which properties, which elements) or they end up in meeting minutes and personal folders.

Health and safety information has its own legal duties and its own people: in the UK, under CDM 2015, the client provides pre-construction information, designers manage design risks, and the principal designer prepares the health and safety file. What those duties often lack is an information plan. That is where the information manager helps.

Basics

How designers find and design out hazards is in Designing out hazards; what the file contains and how it is handed over is in Health and safety information at handover. The design risk register is described in the Pedia. This lesson is about making all of that findable.

Write it into the requirements

Treat safety information as deliverables in the EIR, with the same four answers as any other: what (significant design risks, residual risks, hazardous materials, access and replacement information), who (which designer or contractor), in what form (register rows, element properties, documents) and when (each stage, not only at completion).

InformationProduced byLives inDue
Pre-construction informationClient, with its advisersA published container in the CDEBefore tender
Significant design risksEach designerThe risk register, with element referencesFrom stage 2, updated at each stage
Residual risks for operationDesigners, then contractorsProperties on the elements and assets concernedStage 4, confirmed as built
Hazardous materialsContractor, specialistsAsset data and a dedicated containerAs installed
Health and safety filePrincipal designer (UK)Planned containers plus asset dataBuilt through the project, accepted at handover
Story · The file compiled in a week
How it goes wrong

Nobody plans the health and safety file. In the last week before completion, the principal designer asks every consultant for "anything safety related". Fourteen PDFs arrive, mostly method statements. The operator receives a 900-page file in which the one warning that matters (a fragile roof light over the plant room) is on page 612.

How it goes right

The EIR says residual risks are properties on the elements concerned and rows in the register with element IDs, reviewed at every stage gate. The fragile roof light carries its warning in the model and in the asset data. At handover the file is a short index of containers, and the warning appears in the CAFM whenever a work order is raised for the plant room roof.

Tomhealth and safety advisor
Your turn. Give it about 15 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Map five safety items 15 min

For a new library, map each item to who produces it, when, where it lives in the CDE or model, and who receives it.

  1. Work at height to maintain the atrium glazing.
  2. Lead paint found on retained steelwork.
  3. The method for replacing the main air handling unit.
  4. Isolation points for gas and electricity.
  5. A buried high-voltage cable on the site boundary.

Key takeaways

  • Write safety information into the requirements like any deliverable: what, by whom, in what form, at which milestone.
  • Designers' significant and residual risks are linked to the elements they concern, so they travel with the model to the contractor and the operator.
  • The health and safety file is planned as containers and asset data from the start, and checked at each milestone, not compiled at practical completion.
  • Some safety information is also security-sensitive; agree where the two meet.

Your notes

Related tool

Build an asset register from an IFC and check it on the model: data quality in colour, a data sheet per asset, rooms and systems, a first maintenance plan and tag labels.

Open Asset Register Builder →

Check yourself

3 questions · 2 right to complete
  1. 1. At practical completion nobody can find the designers' residual risks. Why is that most often the case?
  2. 2. Where is a residual risk about replacing a heavy rooftop fan most useful?
  3. 3. Who should check the health and safety information at each milestone?
0 of 3 answered