Chapter 4 recap
Planning and production
The key takeaways from this chapter’s 4 lessons.
Federation strategy and breakdown structure
- The federation strategy says how the project's information is divided into separately produced models, and how those models are combined for coordination.
- The breakdown structure turns that into volumes, levels and information types, which then appear in every container's name.
- Each container has one owner; the responsibility matrix settles who models what at the boundaries (slabs, stairs, ceilings, openings).
- The lead appointed party proposes it in the tender BEP and confirms it at mobilisation; changing it later means renaming and re-planning.
Container metadata: status, revision and classification
- The name identifies the container for its whole life; status, revision and classification are metadata that change or describe it.
- Status (suitability) says what the information may be used for; revision says which version it is; classification says what it is about.
- Shared information uses preliminary revisions (P01, P02); published information uses contractual ones (C01). Work in progress adds a point version (P01.1).
- Codes live in the CDE's metadata and must match what's printed on the drawing; the project's own list in the information standard is the one that counts.
Review, authorisation and acceptance
- The task team checks and reviews its own information before sharing it: names, codes, standard, then content.
- The lead appointed party reviews the whole set across teams and authorises it before submitting it to the client.
- The appointing party reviews the submission against the acceptance criteria in its requirements and accepts or rejects it.
- Each decision is made by a person named in the BEP or the responsibility matrix, and recorded; a rejection goes back with reasons.
Mobilisation
- Mobilisation is when the lead appointed party puts in place the resources, IT and methods promised in its tender, and tests them.
- It confirms the people (available, trained), sets up the CDE (workflows, metadata, access) and tests a real exchange between all teams.
- Problems found go back into the BEP, the information standard and the templates, not into emails.
- The tender's mobilisation plan says what will be tested, by whom and by when; mobilisation ends with a sign-off.