Chapter 3 recap

Tender and appointment

The key takeaways from this chapter’s 3 lessons.

Capability and capacity

  • A tender response shows three things: the team can manage information, can produce it, and has the IT to do both, in the quantities this project needs.
  • Capability is knowing how (standards, methods, tools); capacity is having enough of it at the right time.
  • Each task team assesses itself; the lead appointed party adds them up into one summary for the client.
  • A gap found in tender is a plan; a gap found in production is a delay.

The pre-appointment BEP and the tender response

  • A tender response has four parts: the pre-appointment BEP, a capability and capacity summary, a mobilisation plan and a risk register.
  • The pre-appointment BEP shows who will run information management, how each requirement will be met, how the work is split, and what the team will add to the project’s rules.
  • It is a first version: after appointment the same BEP is confirmed with real names, software and a detailed responsibility matrix.
  • If the client gives a template or headings, use them; it is how responses are compared.

The detailed responsibility matrix

  • There are two matrices: one for information management activities (who sets up the CDE, who checks) and one for information deliverables (who produces what).
  • The deliverables matrix starts high-level at tender and becomes detailed at appointment.
  • The detailed matrix says what information is produced, when and with whom it is exchanged, and which task team produces it.
  • Every line traces back to a requirement; the TIDPs and MIDP then plan the individual containers within its rules.