Chapter 5 recap

Beyond delivery

The key takeaways from this chapter’s 4 lessons.

Security-minded information management

  • ISO 19650-5 starts with a sensitivity assessment by the appointing party: could information about this asset, its users or its contents be used to cause harm or loss?
  • If yes, it sets a security strategy and management plan, puts security requirements into every appointment and limits access to need-to-know.
  • The risk often comes from aggregation (many harmless pieces together) and from publishing: planning portals, marketing images, social media, drone photos.
  • A breach plan says what to do when sensitive information leaks; test it once before it is needed.

The operational phase

  • In operation, the owner or operator is the appointing party; its requirements (OIR, then AIR) define the asset information model (AIM).
  • Trigger events, planned or not, start information work: a repair, a replacement, an inspection, an alteration, a disposal.
  • Each operational appointment carries the relevant part of the AIR and an asset information protocol, and its information is checked and accepted into the AIM.
  • At handover, the project information model is checked and accepted into the AIM; that's the start of the operational phase, not the end of the project.

Health and safety information through the project

  • Write safety information into the requirements like any deliverable: what, by whom, in what form, at which milestone.
  • Designers' significant and residual risks are linked to the elements they concern, so they travel with the model to the contractor and the operator.
  • The health and safety file is planned as containers and asset data from the start, and checked at each milestone, not compiled at practical completion.
  • Some safety information is also security-sensitive; agree where the two meet.

Soft landings

  • Soft landings involve the end users and operators from briefing to the first years of use (in the UK: BS 8536 and Government Soft Landings).
  • The operator's needs go into the OIR and AIR early, so the information delivered is what they will use.
  • Handover is prepared and rehearsed: test data loads, training on the real systems, readiness reviews before completion.
  • Aftercare is planned as information too: what is measured (energy, comfort, faults), by whom, how often, and where the results are kept.