Chapter 1 · Lesson 2 of 2Topic: ISO 19650 basics

Parties, teams and appointments

Appointing party, lead appointed party, appointed party; project team, delivery team, task team. Who is who depends on who appointed whom, and it can change mid-project.

3 min read3 quiz questions
Skip to the quiz

If you already do this for a living: Novation. When a designer moves into the contractor’s team, it stops being a lead appointed party, and its plans, requirements and approvals have to move with it.

  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia

ISO 19650 uses a handful of words for people and organisations. They sound abstract, but each one answers a practical question: who asked for this information, who is accountable for delivering it, and who actually produces it?

Basics

Parties

  • The appointing party is the client, or the organisation managing information for the client.
  • A lead appointed party is appointed directly by the client: a designer, a project manager, a contractor.
  • An appointed party is appointed by a lead appointed party, and is the one that produces the information: a subcontractor, a supplier, a sub-consultant.

Teams

  • A task team is a group doing one task, such as the curtain wall design or the drainage model.
  • A delivery team is one lead appointed party plus all the appointed parties under it.
  • The project team is everyone: the client and every delivery team.

Roles follow appointments

The same company can hold different roles on different projects, or on the same project at different times. What decides the role is the appointment: who signed with whom.

Try it: who is who on your project
Appointing party: the client
Architect · lead appointed party
  • └ Interior designer · appointed party
Engineer · lead appointed party
  • └ Structural engineer · appointed party
  • └ Services engineer · appointed party
Cost consultant · lead appointed party
Main contractor · lead appointed party
  • └ Steelwork subcontractor · appointed party
  • └ Curtain wall subcontractor · appointed party
Lead appointed parties
4
Delivery teams
4
Appointed parties below them5

Every organisation the client appoints directly is a lead appointed party with its own delivery team, even when that team is one firm. Each one needs its own BEP and delivery plan.

On a traditional project the client appoints the architect, the engineers, the cost consultant and later the contractor directly, so there are several lead appointed parties, each with its own delivery team. Under design and build there is often an early design stage with the client’s own designers, then the designers are novated: they move into the contractor’s team.

Story · Novation day
How it goes wrong

The architect is novated to the contractor in month 9. Nobody updates the plans. The architect keeps sharing models straight to the client for approval, as before, while the contractor’s team never sees them in its own review. The contractor builds from the last model it saw, which is two revisions old.

How it goes right

The novation is treated as a change of appointment. The architect’s task information delivery plan moves into the contractor’s master plan, its models go through the contractor’s check before they reach the client, and the BEP’s responsibility matrix is updated the same week.

A delivery team can be one firm

Every lead appointed party has a delivery team, even when that team is just itself. A cost consultant or a project manager appointed by the client produces information (cost plans, programmes, reports) and has the same duties to plan, check and share it. Their information management is simpler, not absent.

Coordinating across delivery teams

Information has to be coordinated within each delivery team (the contractor coordinates its subcontractors) and across delivery teams (the architect’s team and the engineer’s team, both appointed by the client, must agree openings and levels). The second kind is the one that falls between the gaps, because neither lead appointed party is in charge of the other. The client’s information requirements and the project-wide standard are what keep them aligned.

Who does what in information delivery
Appointing partyThe client
Lead appointed partyMain designer or contractor
Task teamsArchitect, engineers, trades
Tender Response Appointment TIDP tasks Shared Submitted↺ needs changes
1Set the information requirementsResult: EIR in the tender
2Answer with a BEPResult: Plan and capability
3Appoint the teamResult: BEP becomes binding
4Mobilise and planResult: MIDP from the TIDPs
5Produce and checkResult: Shared in the CDE
6Review and authoriseResult: Model set approved
7Accept the deliveryResult: Published and kept

Each arrow that crosses a lane is a handoff: one party finishes, another takes over. Dashed: information sent back for changes.

Key takeaways

  • The appointing party is the client (or whoever manages information for it). A lead appointed party is appointed by the client. An appointed party is appointed by a lead appointed party and produces information.
  • Every lead appointed party leads a delivery team, even a team of one. The project team is the client plus all delivery teams.
  • Roles follow appointments, not company types: the same architect can be a lead appointed party before novation and an appointed party after.
  • Information must be coordinated across delivery teams as well as within them.

Your notesSaved in this browser

Related tool

Who is responsible, accountable, consulted and informed for each information management task.

Open Responsibility Matrix →

Check yourself

3 questions · 2 right to complete
  1. 1. A structural engineer is appointed by the main contractor. What is its ISO 19650 role?
  2. 2. The client appoints a cost consultant who works alone. Does the cost consultant need to think about ISO 19650?
  3. 3. At technical design the architect is novated to the design and build contractor. What changes for information management?
0 of 3 answered