Maturity and mandates

Governments and clients increasingly require BIM; maturity models say how far a firm has come. Use both to set the next step, not to win a label.

With Maya, information manager2 min read3 quiz questions
Skip to the quiz
  • Watch out
  • What it costs
  • Experienced readers
  • Remember
  • In BIMpedia
Mayainformation manager
Even if you do this every day, watch for this: A mandate's headline says little. The client's information requirements are what you'll be checked against; read them before you plan anything.

Many governments and large clients now require BIM on their projects, and many firms want to know how far along they are. Mandates and maturity models both help, as long as you treat them as tools for planning, not as labels to claim.

Basics

A mandate is a requirement by a government or client to use BIM on its projects. It is put into practice through the client's own information requirements on each project. A maturity model is a structured self-assessment of how well a firm (or project) does BIM, across areas such as people, process, technology and information, usually on a scale of levels.

Story · Level 2 on paper
How it goes wrong

A firm writes "BIM level 2 compliant" in every tender after buying new software. On its first ISO 19650 project, the client's information manager rejects the first delivery: wrong naming, no status codes, no BEP that matches the client's requirements. The firm spends weeks catching up.

How it goes right

Before bidding, the BIM manager reads the client's information requirements and runs a quick maturity check against them. The gaps are process: naming, a BEP template and a checking routine. They write those, try them on a smaller project, and bid with a BEP that answers the client's requirements point by point.

A simple maturity check

AreaAskEvidence
PeopleWho can do what? Who leads?Roles, skills matrix
ProcessAre there templates, naming rules, checks?BEP template, standards, checklists
TechnologyDo tools and IT support the work?Software, hardware, CDE
InformationIs what we deliver structured and checked?Recent deliveries, client feedback
Mayainformation manager
Your turn. Give it about 10 min and work it out on your own before you open the model answer: that is where it sticks.
Exercise: Plan the next step 10 min

A firm's quick check: People 3/5, Process 1/5, Technology 4/5, Information 2/5. A public client's ISO 19650 project is coming up in four months.

Check yourself

Where to start?

Quick check: People 3/5, Process 1/5, Technology 4/5, Information 2/5. A public ISO 19650 project starts in four months. What comes first?

Key takeaways

  • A mandate is what a client or government requires; read the actual requirement, not the headline.
  • A maturity assessment is useful for finding the next step, not for scoring the firm.
  • Assess a few areas honestly: people, process, technology, information.
  • Plan one level of improvement at a time, starting where projects hurt most.

Your notes

Check yourself

3 questions · 2 right to complete
  1. 1. A public client's tender says 'BIM required in line with ISO 19650'. What should you do first?
  2. 2. A maturity assessment shows the firm scores high on software and low on process. What's the best next step?
  3. 3. What is a maturity assessment most useful for?