BEP (BIM execution plan)

The delivery team’s plan for how it will produce, check and deliver information to meet the client’s requirements.
Updated 5 November 2026Draft · awaiting review

A BIM execution plan (BEP) explains how a delivery team will manage information on a project: who produces what, with which tools and standards, how it is checked and shared, and how it meets the client's information requirements. In ISO 19650 terms it is the delivery team's response to the exchange information requirements (EIR).

At a glance

Written byThe lead appointed party (for example the lead designer or main contractor), with its task teams
Responds toThe appointing party's EIR
Defined inISO 19650-2 (pre- and post-appointment BEP)
UpdatedAt appointment, then whenever the team, scope or methods change
Typical length20–60 pages plus appendices

Two versions

Pre-appointment BEPPost-appointment BEP
WhenWith the tenderAfter appointment, before production starts
PurposeShows the team can meet the EIRThe working plan everyone follows
ContentsProposed approach, key people, capability, initial milestonesConfirmed roles, methods, schedules, standards and appendices

What a BEP usually contains

  • Project information: scope, stages, key dates and the parties involved.
  • Roles and responsibilities: information management roles and who fills them, often in a responsibility matrix.
  • Information delivery strategy: how the federated model is split (by discipline, zone or building), and how teams depend on each other.
  • Standards and methods: the information standard, naming convention, classification, units, coordinates and level of information need.
  • Software and formats: authoring tools, versions, exchange formats such as IFC and BCF, and the CDE.
  • Coordination procedures: model sharing frequency, clash testing, tolerances and the meeting cycle.
  • Quality checks: what is checked before sharing and how results are recorded.
  • Delivery plans: the master information delivery plan (MIDP) and task information delivery plans (TIDP), or references to them.

Appendices often hold the parts people use daily: the clash test matrix, LOD/LOIN matrix, naming rules and model breakdown.

How information requirements cascade into delivery plans
OIROrganisational needs
AIRAsset needs
PIRProject needs
DeliveryAt agreed milestones

Requirements flow from the client’s needs into the EIR; the delivery team answers with the BEP and delivery plans.

How it is used

The BEP is a contract-adjacent document: it records what the team agreed to do. During delivery it settles practical questions ("which tolerance do we use for ducts against beams?") and is the reference for audits. New team members read it first.

Common misunderstandings

  • A BEP is not a template. A generic BEP copied from another project usually contradicts the actual EIR, software and team.
  • It isn't finished at tender. The post-appointment BEP is where the detail lives, and it changes as the project does.
  • More pages don't mean more control. The coordination rules, tolerances and checks matter more than general descriptions of BIM.
  • It is not the EIR. The EIR says what the client needs; the BEP says how the team will provide it.

Where to read more

ISO 19650-2 describes the BEP's place in the appointment process. Many national bodies publish BEP templates (for example the UK BIM Framework guidance); use them as a checklist, not as text to submit.