Responsibility matrix

The table that assigns who produces, checks and approves each piece of information and each information management task, at high and detailed levels.
Updated 5 November 2026Draft · awaiting review

A responsibility matrix sets out who is responsible for each information deliverable and each information management task on a project. ISO 19650 uses two levels: a high-level matrix that assigns deliverables to task teams, and a detailed matrix that names who produces what, at what level of information need, and when. Many projects also keep a matrix for information management functions themselves.

At a glance

High-levelDetailed
Prepared byThe lead appointed party, at tenderThe lead appointed party with task teams, after appointment
AssignsDeliverables and responsibilities to task teamsEach information container to an author, with its LOIN and milestone
FeedsThe pre-appointment BEPThe TIDPs and MIDP
Defined inISO 19650-2ISO 19650-2

Common formats

RACI is a common way to fill the cells:

LetterMeaning
RResponsible: does the work
AAccountable: approves it; one per row
CConsulted: gives input before
IInformed: told after

A matrix for information management tasks might look like:

TaskClientLead designerContractorTask teams
Write the EIRA/RCII
Set up the CDEARCI
Write the BEPIA/RCC
Produce discipline modelsIAIR
Run clash coordinationIA/RCC
Deliver asset dataACRR

What it prevents

  • Elements nobody models because each team assumed another would.
  • Elements modelled twice by two teams.
  • Checks and approvals that nobody performs.
  • Disputes later about who should have provided information.

Common mistakes

  • Several "A"s in one row, so accountability is shared and nobody holds it.
  • Organisations instead of people in the detailed matrix.
  • Not updated when the team or scope changes.
  • Disconnected from the MIDP, so responsibilities and deliverables drift apart.

Where to read more

ISO 19650-2 describes both matrices in the tender and appointment stages. National guidance gives templates for information management functions.