Chapter 2 recap

Coordination

The key takeaways from this chapter’s 3 lessons.

Setting up clash tests that matter

  • Decide in advance which discipline pairs are tested, with what type, tolerance and priority. Write it down as a clash matrix.
  • Choose tolerances that ignore modelling noise but catch real problems.
  • Every test needs an owner who is expected to resolve its clashes.
  • Group raw clashes into issues before a meeting. People resolve issues, not clash counts.

Running a coordination meeting

  • Prepare before the meeting: federate shared models, run tests, group clashes into issues.
  • Use a fixed agenda so the meeting becomes a routine, not a debate about what to discuss.
  • Review issues in priority order, in the model, and record a decision for each one.
  • Send minutes and the updated issue log within a day, and start the next meeting from the open items.

Tracking issues to closure

  • Use a small set of statuses with clear meanings: Open, In progress, Resolved, Closed.
  • Resolved means the owner says it is fixed; Closed means it has been verified in a new shared model.
  • Every issue has one owner, a due date and a reference to where it can be seen in the model.
  • Watch overdue issues and the trend of open issues over time, not just the total count.