Chapter 1 recap

Information management basics

The key takeaways from this chapter’s 3 lessons.

What ISO 19650 asks of a project team

  • ISO 19650 is a framework for managing information, not a modelling standard or a software requirement.
  • Every requirement flows down: the appointing party says what it needs, delivery teams plan how and when to provide it.
  • Roles matter more than job titles: appointing party, lead appointed party and appointed parties.
  • Information is produced in a common data environment and moves through agreed states before anyone relies on it.

EIR, BEP, MIDP and TIDP explained

  • The EIR says what information the appointing party needs from an appointment, and why.
  • The BEP is the delivery team's answer: how it will meet the requirements, with which people, processes and tools.
  • Each task team writes a TIDP listing what it will deliver and when.
  • The lead appointed party combines the TIDPs into the MIDP, the delivery team's master schedule of information.

The CDE and its states

  • The CDE is both a set of tools and an agreed workflow for managing information containers.
  • Work in progress is visible only to the task team that produces it.
  • Shared information has been checked and can be used by others for coordination, but it is not yet approved for construction or handover.
  • Published information is authorised for its intended use; archived keeps the full history.